 "attribution": {
  "license": "CC BY 4.0",
  "license_url": "https://creativecommons.org/licenses/by/4.0/",
  "cite_as": "Eurodatum (https://eurodatum.com/ai-campuses/), data: Our World in Data/Ember, Eurostat, checked 2026-11-19",
  "required": "Credit 'Eurodatum' with a link to the page_url when quoting numbers, charts or definitions.",
  "page_url": "https://eurodatum.com/ai-campuses/",
  "publisher": "Eurodatum by Cynsta Technologies s.r.o.",
  "publisher_url": "https://www.cynsta.com",
  "home": "https://eurodatum.com/"
 },
 "campuses": [
  {
   "name": "Stargate Norway",
   "country": "norway",
   "city": "Narvik",
   "lat": 68.44,
   "lon": 17.43,
   "precision": "site",
   "developer": "Nscale & Aker (JV), OpenAI as offtaker",
   "mw_initial": 230,
   "mw_max": 520,
   "gpus": "100,000 NVIDIA GPUs targeted by end of 2026",
   "status": "announced",
   "year_announced": 2025,
   "target": "2026",
   "power": "Renewable (hydro)",
   "note": "230 MW initial, ambition to add 290 MW.",
   "source": "https://www.nscale.com/press-releases/stargate-norway-nscale-aker-openai",
   "source_type": "primary"
  },
  {
   "name": "Fluidstack AI supercomputer, France",
   "country": "france",
   "city": "France (site not disclosed)",
   "lat": 48.86,
   "lon": 2.35,
   "precision": "approx",
   "developer": "Fluidstack (MoU with French government)",
   "mw_initial": 1000,
   "mw_max": null,
   "gpus": "~500,000 next-generation chips in phase 1",
   "status": "mou",
   "year_announced": 2025,
   "target": "Phase 1 from 2026, beyond 1 GW by 2028",
   "power": "Predominantly nuclear",
   "note": "€10bn initial investment.",
   "source": "https://www.fluidstack.io/post/1gw-ai-supercomputer-france",
   "source_type": "primary"
  },
  {
   "name": "Mistral AI × EcoDataCenter",
   "country": "sweden",
   "city": "Borlänge",
   "lat": 60.49,
   "lon": 15.44,
   "precision": "site",
   "developer": "EcoDataCenter, Mistral AI",
   "mw_initial": 250,
   "mw_max": 600,
   "gpus": "NVIDIA Vera Rubin",
   "status": "announced",
   "year_announced": 2026,
   "target": "2027",
   "power": "Swedish grid (low-carbon)",
   "note": "€1.2bn; Mistral's first AI infrastructure outside France.",
   "source": "https://www.datacenterdynamics.com/en/news/french-ai-firm-mistral-signs-12bn-deal-to-lease-ecodatacenter-facility-in-sweden/",
   "source_type": "secondary"
  },
  {
   "name": "Start Campus Sines (Nscale for Microsoft)",
   "country": "portugal",
   "city": "Sines",
   "lat": 37.95,
   "lon": -8.87,
   "precision": "site",
   "developer": "Start Campus; Nscale for Microsoft",
   "mw_initial": 200,
   "mw_max": 1200,
   "gpus": "12,600+ Blackwell Ultra (SIN01); 66,000+ Rubin from late 2027",
   "status": "partly-live",
   "year_announced": 2025,
   "target": "Late 2027 (second building)",
   "power": "Grid + renewables",
   "note": "Campus permitted for 1.2 GW; €465m for a second 200 MW building.",
   "source": "https://www.nscale.com/press-releases/nscale-start-campus",
   "source_type": "primary"
  },
  {
   "name": "Nscale Loughton",
   "country": "united-kingdom",
   "city": "Loughton, Essex",
   "lat": 51.65,
   "lon": 0.07,
   "precision": "site",
   "developer": "Nscale",
   "mw_initial": 50,
   "mw_max": 90,
   "gpus": "23,040 GPUs planned for Azure",
   "status": "delayed",
   "year_announced": 2025,
   "target": "Was Q4 2026; grid power now expected in the 2030s",
   "power": "Grid (delayed)",
   "note": "Microsoft reported to have withdrawn (Oct 2026); Nscale exploring alternative power.",
   "source": "https://datacenterdynamics.com/en/news/microsoft-pulls-out-of-delayed-nscale-data-center-in-loughton-essex",
   "source_type": "secondary"
  },
  {
   "name": "Mistral training cluster (Eclairion)",
   "country": "france",
   "city": "Essonne",
   "lat": 48.59,
   "lon": 2.19,
   "precision": "site",
   "developer": "Eclairion, Fluidstack, Mistral AI",
   "mw_initial": null,
   "mw_max": null,
   "gpus": null,
   "status": "announced",
   "year_announced": 2025,
   "target": null,
   "power": "French grid (nuclear)",
   "note": "Multi-year hosting deal for Mistral's training cluster.",
   "source": "https://datacenterdynamics.com/en/news/gpu-cloud-provider-fluidstack-signs-mou-for-1gw-ai-supercomputer-in-france",
   "source_type": "secondary"
  },
  {
   "name": "Azora / Tillion data campus",
   "country": "spain",
   "city": "Villamayor de Gállego, Zaragoza",
   "lat": 41.68,
   "lon": -0.77,
   "precision": "site",
   "developer": "Azora, Tillion",
   "mw_initial": null,
   "mw_max": 300,
   "gpus": null,
   "status": "announced",
   "year_announced": 2025,
   "target": null,
   "power": null,
   "note": "Initial €1.1bn, up to €2bn.",
   "source": "https://blackridgeresearch.com/blog/largest-latest-top-upcoming-data-centers-in-europe-list",
   "source_type": "secondary"
  },
  {
   "name": "Microsoft Zaragoza campus",
   "country": "spain",
   "city": "Aragón",
   "lat": 41.65,
   "lon": -0.88,
   "precision": "approx",
   "developer": "Microsoft",
   "mw_initial": null,
   "mw_max": null,
   "gpus": null,
   "status": "announced",
   "year_announced": null,
   "target": "Construction from 2026",
   "power": null,
   "note": "About $3.4bn; capacity not disclosed.",
   "source": "https://blackridgeresearch.com/blog/largest-latest-top-upcoming-data-centers-in-europe-list",
   "source_type": "secondary"
  },
  {
   "name": "DC Malpica AI campus",
   "country": "spain",
   "city": "Mora, Toledo",
   "lat": 39.68,
   "lon": -3.77,
   "precision": "site",
   "developer": "DC Malpica",
   "mw_initial": null,
   "mw_max": 300,
   "gpus": null,
   "status": "announced",
   "year_announced": 2026,
   "target": null,
   "power": null,
   "note": "Announced July 2026.",
   "source": "https://cloudnews.tech/europes-data-center-boom-over-3-2-gw-announced-in-a-single-month/",
   "source_type": "secondary"
  },
  {
   "name": "Apto Lacchiarella campus",
   "country": "italy",
   "city": "Lacchiarella, Milan",
   "lat": 45.32,
   "lon": 9.14,
   "precision": "site",
   "developer": "Apto",
   "mw_initial": null,
   "mw_max": 300,
   "gpus": null,
   "status": "announced",
   "year_announced": 2025,
   "target": null,
   "power": null,
   "note": "About $3.4bn.",
   "source": "https://blackridgeresearch.com/blog/largest-latest-top-upcoming-data-centers-in-europe-list",
   "source_type": "secondary"
  },
  {
   "name": "EdgeConneX Lombardy campuses",
   "country": "italy",
   "city": "Lombardy",
   "lat": 45.46,
   "lon": 9.19,
   "precision": "approx",
   "developer": "EdgeConneX",
   "mw_initial": null,
   "mw_max": 300,
   "gpus": null,
   "status": "announced",
   "year_announced": 2025,
   "target": "2031",
   "power": null,
   "note": "€3bn across three campuses, total above 300 MW.",
   "source": "https://blackridgeresearch.com/blog/largest-latest-top-upcoming-data-centers-in-europe-list",
   "source_type": "secondary"
  },
  {
   "name": "QTS Vimercate",
   "country": "italy",
   "city": "Vimercate, Milan",
   "lat": 45.61,
   "lon": 9.37,
   "precision": "site",
   "developer": "QTS Data Centers",
   "mw_initial": null,
   "mw_max": 220,
   "gpus": null,
   "status": "announced",
   "year_announced": 2025,
   "target": null,
   "power": null,
   "note": "Up to €2.3bn.",
   "source": "https://blackridgeresearch.com/blog/largest-latest-top-upcoming-data-centers-in-europe-list",
   "source_type": "secondary"
  },
  {
   "name": "Sesterce Jämsä (Kaipola)",
   "country": "finland",
   "city": "Jämsä",
   "lat": 61.86,
   "lon": 25.19,
   "precision": "site",
   "developer": "Sesterce",
   "mw_initial": 200,
   "mw_max": 600,
   "gpus": null,
   "status": "announced",
   "year_announced": 2026,
   "target": "Phase 1 construction from 2026",
   "power": "Finnish grid; 1 MW new renewables per MW used",
   "note": "More than €10bn; former Kaipola paper mill; anchor customer not named.",
   "source": "https://datacenterdynamics.com/en/news/sesterce-to-invest-10bn-in-600mw-ai-data-center-campus-in-j%C3%A4ms%C3%A4-finland",
   "source_type": "secondary"
  },
  {
   "name": "Cerebras × Compute Nordic Mikkeli",
   "country": "finland",
   "city": "Mikkeli",
   "lat": 61.69,
   "lon": 27.27,
   "precision": "site",
   "developer": "Compute Nordic Finland, Cerebras",
   "mw_initial": 50,
   "mw_max": 165,
   "gpus": "Cerebras systems",
   "status": "in-build",
   "year_announced": 2026,
   "target": "50 → 80 → 165 MW in phases",
   "power": "Finnish grid; waste-heat recovery",
   "note": "Seven-year service orders; €1.0–1.7bn indicative investment (Ramboll).",
   "source": "https://www.datacenterdynamics.com/en/news/cerebras-starts-construction-on-165mw-data-center-in-mikkeli-finland/",
   "source_type": "secondary"
  },
  {
   "name": "atNorth Varde (DEN02)",
   "country": "denmark",
   "city": "Varde",
   "lat": 55.62,
   "lon": 8.48,
   "precision": "site",
   "developer": "atNorth",
   "mw_initial": 500,
   "mw_max": null,
   "gpus": null,
   "status": "announced",
   "year_announced": null,
   "target": null,
   "power": "Danish grid (wind)",
   "note": "AI-ready colocation mega site; path to several hundred MW more.",
   "source": "https://www.atnorth.com/nordic-data-centers/future-sites/",
   "source_type": "primary"
  },
  {
   "name": "atNorth Myllykoski (FIN04)",
   "country": "finland",
   "city": "Myllykoski",
   "lat": 60.77,
   "lon": 26.78,
   "precision": "site",
   "developer": "atNorth",
   "mw_initial": 430,
   "mw_max": null,
   "gpus": null,
   "status": "announced",
   "year_announced": null,
   "target": null,
   "power": "Finnish grid",
   "note": "AI-ready colocation mega site; path to several hundred MW more.",
   "source": "https://www.atnorth.com/nordic-data-centers/future-sites/",
   "source_type": "primary"
  },
  {
   "name": "atNorth Salo (FIN05)",
   "country": "finland",
   "city": "Salo",
   "lat": 60.38,
   "lon": 23.13,
   "precision": "site",
   "developer": "atNorth",
   "mw_initial": null,
   "mw_max": 230,
   "gpus": null,
   "status": "announced",
   "year_announced": null,
   "target": null,
   "power": "Finnish grid",
   "note": "230 MW campus power, up to 160 MW IT.",
   "source": "https://www.atnorth.com/nordic-data-centers/future-sites/",
   "source_type": "primary"
  },
  {
   "name": "atNorth Sollefteå (SWE04)",
   "country": "sweden",
   "city": "Långsele, Sollefteå",
   "lat": 63.18,
   "lon": 17.07,
   "precision": "site",
   "developer": "atNorth",
   "mw_initial": null,
   "mw_max": 300,
   "gpus": null,
   "status": "announced",
   "year_announced": null,
   "target": null,
   "power": "Swedish grid (hydro)",
   "note": "300 MW planned.",
   "source": "https://www.atnorth.com/nordic-data-centers/future-sites/",
   "source_type": "primary"
  },
  {
   "name": "atNorth Haugaland (NOR01)",
   "country": "norway",
   "city": "Tysvær",
   "lat": 59.36,
   "lon": 5.4,
   "precision": "site",
   "developer": "atNorth",
   "mw_initial": 120,
   "mw_max": 350,
   "gpus": null,
   "status": "announced",
   "year_announced": null,
   "target": null,
   "power": "Norwegian grid (hydro)",
   "note": "Haugaland Business Park; 350 MW planned ramp-up.",
   "source": "https://www.atnorth.com/nordic-data-centers/future-sites/",
   "source_type": "primary"
  },
  {
   "name": "Schwarz Group Lübbenau",
   "country": "germany",
   "city": "Lübbenau",
   "lat": 51.87,
   "lon": 13.96,
   "precision": "site",
   "developer": "Schwarz Group (Lidl owner)",
   "mw_initial": 200,
   "mw_max": null,
   "gpus": "Up to 100,000 GPUs expected",
   "status": "in-build",
   "year_announced": 2025,
   "target": null,
   "power": "Former lignite power plant site",
   "note": "Ground broken; about €11bn reported.",
   "source": "https://www.datacenterdynamics.com/en/news/deutsche-telekom-and-lidl-owner-schwarz-group-to-build-ai-data-center-in-germany-report/",
   "source_type": "secondary"
  },
  {
   "name": "Deutsche Telekom × NVIDIA Industrial AI Cloud",
   "country": "germany",
   "city": "Munich",
   "lat": 48.14,
   "lon": 11.58,
   "precision": "approx",
   "developer": "Deutsche Telekom, NVIDIA",
   "mw_initial": null,
   "mw_max": null,
   "gpus": "Up to 10,000 NVIDIA GPUs",
   "status": "announced",
   "year_announced": 2025,
   "target": "Build from 2026",
   "power": null,
   "note": "About €1bn; Telekom expects ~50% more AI compute in Germany.",
   "source": "https://rcrwireless.com/20250808/ai-infrastructure/deutsche-telekom",
   "source_type": "secondary"
  },
  {
   "name": "QTS Cambois campus (North East AI Growth Zone)",
   "country": "united-kingdom",
   "city": "Blyth, Northumberland",
   "lat": 55.16,
   "lon": -1.53,
   "precision": "site",
   "developer": "QTS (Blackstone)",
   "mw_initial": null,
   "mw_max": 720,
   "gpus": null,
   "status": "announced",
   "year_announced": 2025,
   "target": null,
   "power": "Zone plan: 1.1 GW within six years",
   "note": "£10bn campus in a designated AI Growth Zone.",
   "source": "https://researchbriefings.files.parliament.uk/documents/CBP-10315/CBP-10315.pdf",
   "source_type": "primary"
  },
  {
   "name": "Culham AI Growth Zone",
   "country": "united-kingdom",
   "city": "Culham, Oxfordshire",
   "lat": 51.66,
   "lon": -1.23,
   "precision": "site",
   "developer": "UKAEA (site), partner TBC",
   "mw_initial": 100,
   "mw_max": 500,
   "gpus": null,
   "status": "announced",
   "year_announced": 2025,
   "target": null,
   "power": "~100 MW initial, expansion explored to 500 MW",
   "note": "First UK AI Growth Zone (January 2025).",
   "source": "https://researchbriefings.files.parliament.uk/documents/CBP-10315/CBP-10315.pdf",
   "source_type": "primary"
  },
  {
   "name": "DataVita (Scotland AI Growth Zone)",
   "country": "united-kingdom",
   "city": "North Lanarkshire",
   "lat": 55.83,
   "lon": -3.98,
   "precision": "approx",
   "developer": "DataVita",
   "mw_initial": null,
   "mw_max": 500,
   "gpus": null,
   "status": "announced",
   "year_announced": 2026,
   "target": null,
   "power": null,
   "note": "Designated AI Growth Zone could unlock 500 MW.",
   "source": "https://www.datacenterdynamics.com/en/news/new-ai-growth-zone-in-north-lanarkshire-scotland-could-unlock-500mw-of-data-center-capacity/",
   "source_type": "secondary"
  },
  {
   "name": "VOLT Rotterdam AI Gigafactory",
   "country": "netherlands",
   "city": "Rotterdam (Maasvlakte)",
   "lat": 51.95,
   "lon": 4.03,
   "precision": "site",
   "developer": "VOLT; Nebius as first offtaker (LOI)",
   "mw_initial": 200,
   "mw_max": 600,
   "gpus": null,
   "status": "mou",
   "year_announced": 2026,
   "target": "First capacity late 2029 / 2030",
   "power": "Eneco",
   "note": "Phase 1: two buildings, 200 MW, about €7bn. Nebius LOI is non-binding.",
   "source": "https://datacenterdynamics.com/en/news/nebius-signs-loi-with-volt-for-data-center-capacity-in-rotterdam-the-netherlands",
   "source_type": "secondary"
  },
  {
   "name": "Telefónica-led AI Gigafactory bid",
   "country": "spain",
   "city": "Móra la Nova, Tarragona",
   "lat": 41.1,
   "lon": 0.65,
   "precision": "site",
   "developer": "Telefónica-led consortium",
   "mw_initial": null,
   "mw_max": null,
   "gpus": null,
   "status": "bid",
   "year_announced": 2026,
   "target": "EU decision expected early 2027",
   "power": null,
   "note": "Bid for the EU AI Gigafactories call (sites of up to ~150 MW).",
   "source": "https://www.datacenterdynamics.com/en/news/cities-across-europe-line-up-to-host-eus-ai-gigafactories/",
   "source_type": "secondary"
  }
 ]
}